Location: Baghdad, Iraq with travel to Amman, Jordan
Application Deadline: 23-Jan-13
Type of Contract: Individual Contract
Post Level: National Consultant
Languages Required: Arabic
English
Starting Date: (Date when the selected candidate is expected
to start) 03-Feb-2013
Duration of Initial Contract: 40 Working Days Over a period
of 6 Month.
Background |
|
Important Notes: All necessary information including Complete Terms of Reference, Selection Criteria, and Annexes are found on the following link under Procurement Notice Number IC-003/13: http://www.iq.undp.org/ProcurementNotices_Overview.aspx Proposals should be submitted to the following e-mail address no later than COB 23rd of January 2013 (Amman Time +3GMT): SSA.undp.iraq@undp.org
Iraq has set a clear direction for the energy sector, which accommodates the development of renewable energy technologies, mainly to address the gap between demand and supply and recognizing the huge potential for solar power to do so. This is recognized as ultimately making a significant contribution to reduction of greenhouse gas emissions currently associated with the Iraqi energy sector. This renewable energy direction is further reinforced in the recent (May 2011) Joint Declaration signed by Iraq and the European Union, in which sustainable energy in Iraq is explicitly mentioned, including generation from low and zero-carbon emission sources. The reliability and capacity of Iraq’s electricity supply have fallen since 2002. At that time, electricity supply capacity was 9,300 MW, with peak loads of 5,100 MW. The current electricity supply in operation is about 4,500 MW, with demand of almost 10,000 MW, which creates a huge challenge: about 6 GW of new power is required in the near-term. Approximately 80% of Iraqis are on-grid, with over 80% of grid-supplied electricity coming from hydrocarbon-fueled power plants. A small amount, less than 20%, comes from hydropower. Iraqis have increased their demand for electricity (through population growth and increased electricity requirements in homes and offices), but the reliability of supply is inadequate and load-shedding is a common daily experience (for example, in Baghdad, electricity is supplied for only about 14 hours per day, rolling on-and-off). Many households and businesses therefore rely on diesel-powered generators to fill the demand-supply gap, which increases the cost of electricity significantly. The Ministry of Electricity Master Plan for 2010-2030 indicates that 10,000 MW of fossil-fuelled plants need to be in place by 2013 to meet expected demand and to overcome the current shortfall in supply. Other units to be considered after 2013 will be based on the projected increase in demand, and a combination of Government and private-sector finance will be required. Residual Heavy Fuel Oil (HFO) is expected to be the primary fuel for the initial 10,000 MW, whereas natural gas, distillates and renewables – particularly solar power – will be brought on stream after 2013. The most compelling renewable energy source in Iraq (at this time) appears to be solar, mostly reflecting the pervasive nature of this energy source (in time and space) and the opportunity to develop distributed generation systems with minimal dependencies on existing infrastructure and institutional processes, but also with a significant potential to feed back into the electricity grid during peak load periods. In addition, there is significant opportunity for private sector deployment in the solar power sector, especially given the expected increasing consumer demand for solar-powered appliances (air conditioners in particular, and water heaters) and given the construction of “model” towns (for example, near Najaf, south of Baghdad), where the intention of developers is to remain non-reliant on the grid, ensure a reliable supply of clean electricity, and develop cost recovery mechanisms that will support the initial investments (including selling electricity back to the grid). Iraq has made some initial ventures into solar power use. A number of cities in Iraq have installed solar-powered street lights and solar water heaters, but these cases have not been well-documented and there is anecdotal information that some of the street lighting is ineffective. Extreme high temperatures and increasingly frequent dust storms present some additional challenges for solar PV panels. Careful comparative research into options and some innovation in creating cooling flows to panels and self-cleaning functions are required. In addition, provision of air conditioning at night is still a key requirement, and some element of grid connectivity or hybridization of traditional compressor technology and absorption cooling, in combination with PV panel support to such a unit, may be required. Some comparative work on various solar power air conditioner technologies has already been done by the Ministry of Science and Technology (MoST). MoST has devoted considerable efforts to exploring a range of hybrid rooftop units that utilize PV and also solar thermal energy; the PV-generated electricity can be used for household consumption and/or to provide electrical supply to run (where applicable) a unit’s fans and/or pumps and/or cooling loop-vent to reduce the surface temperature of the PV panels themselves (thereby increasing their efficiency in very hot conditions). While various technology comparisons and assessments have been undertaken, there is as yet no strategic approach which focuses on the highest critical electricity consumption appliances (air conditioners) and the need for reliable distributed electricity supply in new residential development areas. The recently-approved UNDP-GEF project will advance on the work done to date in Iraq with regard to solar power technologies. It will clarify the most practical and affordable combination of solar power air conditioning/water heating options that can meet the operational conditions in Iraq (solar thermal systems, PV systems and/or hybrid systems), addressing the most critical electricity demands in houses, offices and small businesses throughout Iraq. The project will organize the comparative technology assessments completed to date, and catalyze the actual procurement and assembly of parts (or complete units), install them in a manner that allows further monitoring for effectiveness, and at the same time bring benefits to the users, which will help with the eventual replication of installations and spur Iraqi industrial development in this area. The same philosophy is expected with the design and construction / operation of a 5MW solar PV power plant (there are no such plants in Iraq at the moment, although the Ministry of Electricity would like to build 16 larger-scale solar power plants over the next five years). Policy-level work will focus on the development of approved and enforced policies and regulations, and new financial incentives, to encourage solar power industry development (private sector) and consumer uptake, including removal of import tariffs on components; introduction of subsidies and tax credits to promote investment in, and installation of, solar units; increased taxes on non-solar AC units; development of a renewable energy database containing site-specific data on RE potential to facilitate investment decisions; and clarification of IPP policies, with inducements to accelerate solar PV power plant development throughout Iraq. Examination of inter-connections between distributed power producers and the grid (including feed-in tariffs and net metering options) and support to the Government to implement feed-in tariff and/or net-metering schemes. One selected measure will be framed as a Nationally Appropriate Mitigation Action (NAMA), with corresponding baseline, MRV and institutional systems developed. The UNDP-GEF project will advance solar energy uptake in Iraq in three ways:
The project has been granted a 9-month Project Preparation phase, commencing in November 2012, culminating in the submission of a completed CEO Endorsement Request and UNDP Project Document to the GEF Secretariat by July 2013. Specific project preparation (PPG) activities will focus on: conducting a more detailed assessment of the market for decentralised solar units and utility-scale solar electricity generation; greenhouse gas (GHG) baseline/reduction potential in Iraq; a study/dialogue on advancing the IPP concept and the technical aspects of grid inter-connection; mapping and coordinating stakeholders; and completing project documentation.
|
|
Duties and Responsibilities |
|
Objectives: The UNDP Iraq Country Office (based in Amman, Jordan) wishes to prepare a GEF CEO Endorsement Request and a UNDP Project Document for the recently-approved GEF project, ‘Catalysing the use of solar photovoltaic energy’. The National Consultant, working with an International Consultant, will take the lead in preparing these documents. Scope and expected outputs: Under the overall guidance of UNDP Country Office Focal Point for Environment & Energy, and in coordination with the International Consultant, and as informed by guidance from the UNDP/GEF Regional Technical Advisor, the National Consultant (acting in his/her individual capacity) will be tasked with the following duties and responsibilities: Component 1: Investment in solar power technologies for distributed electricity generation for office, small business, residential and small town application. Expected Outcome: concrete evidence of the utility, practicality and competitive advantage of rooftop solar AC/water heater systems for office, small business and residential application and the viability of distributed, small-scale (5 MW) solar PV power plants for small town services, leading to replication of the solar technology applications that were demonstrated and increased investments in such technologies.
Component 2: Encouragement of investments in solar power technology in Iraq and consumer uptake of solar appliances through policy reform, tools and financial incentives. Expected Outcome: Enhanced private investment in, and consumer uptake of, solar technologies (rooftop appliances and distributed solar PV power plants).
Expected Outcome: Widespread awareness and increased private sector capacity for the supply and servicing of solar air conditioners and water heaters; and increased Government and private sector capacity for the design, construction and operation of small-scale, distributed solar power plants leading to: (1) increased installed capacity of operational distributed solar power plants that are locally designed, engineered, constructed and operated; and (2) increased volume of locally-manufactured solar AC/water heater units.
Working with the International Consultant, define the project scope and logical framework based on the results of the above analysis, the approved Project Identification Form (PIF), comments from the GEF Secretariat, comments from the GEF Scientific & Advisory Panel (STAP), feedback from the UNDP Country Office and Regional Technical Advisor, and other stakeholders:
While UNDP will be responsible for the logistic costs of the participants. The Consultant Under the direct supervision of the requesting unit is requested to produce for the following deliverables:
|
|
Competencies |
|
Key Performance Indicators during implementation of Services:
Corporate Values:
| |
Required Skills and Experience |
|
Education:
Proposals: Documents to be included when submitting the Proposal: Technical Proposal: (Which will include the following):
The financial proposal will specify a total lump sum amount and payment terms around specific and measurable (qualitative and quantitative) deliverables. Payments are based upon output, i.e. upon delivery of the services specified in the TOR. A breakdown of this lump sum amount is to be provided by the IC candidate. Total Fees: Please use Annex 3 – Financial proposal form. All necessary information including: Complete Terms of Reference, The Selection Criteria, and Annexes are found on the following link under Procurement Notice Number IC-003/12: http://www.iq.undp.org/ProcurementNotices_Overview.aspx Proposals should be submitted to the following e-mail address no later than COB 23rd of January 2013 (Amman Time +3GMT): SSA.undp.iraq@undp.org |
|
UNDP is committed to achieving workforce
diversity in terms of gender, nationality and culture. Individuals from
minority groups, indigenous groups and persons with disabilities are
equally encouraged to apply. All applications will be treated with the
strictest confidence.
|
Social Plugin